Mason household
2026-04-08 · Wivenhoe CO7
lost timeline
£15,756
7
Summary
LOST: Resin-bound driveway 70sqm — timeline mismatch
Quoted: full resin-bound driveway 70sqm, Buff blend, edging course, drainage tie-in.
Line items
- Excavate + dispose existing70 sqm · £1,400
- Type 1 subbase15 tonne · £900
- Resin-bound aggregate (Buff)70 sqm · £6,650
- Edging course32 linear m · £1,120
- Drainage tie-in1 job · £420
- Mini-digger 2 days + crew labour1 job · £2,640
Subtotal£13,130
VAT (20%)£2,626
Total£15,756
Crew
—
Internal · Never sent to customer
Payment: n/a
Notes: Customer needed it done in 2 weeks; our soonest slot was 6 weeks out. Lost the job. Worth tracking if our schedule loosens; 4-6 week lead time is the norm for substantial driveways. Don't sacrifice scheduling discipline for a single job — Harry+Bukayo are the bottleneck, can't double-book.