Cope residence
2025-11-04 · Colchester CO2
won
£5,688
3
Summary
Concrete pad for garden room (8x4m) + drainage
Excavate 8x4m base, lay 150mm Type 1 subbase, reinforced concrete pad 150mm with mesh, drainage gravel surround, tie-in to existing soakaway.
Line items
- Excavation 8x4m (mini-digger 1 day)1 day · £400
- Type 1 subbase 150mm (10 tonne)10 tonne · £600
- Reinforced concrete pad + mesh32 sqm · £2,080
- Drainage gravel + soakaway tie-in1 job · £520
- Skip 8-yard1 skip · £300
- Crew labour3 person-day · £840
Subtotal£4,740
VAT (20%)£948
Total£5,688
Crew
Harry, Jude
Internal · Never sent to customer
Payment: 50% deposit, balance on completion, paid promptly
Notes: Concrete pad only — customer's preferred garden-room supplier did the building separately. Sequencing: pad must cure 7 days before structure delivery; coordinate. Note: customer asked about full garden-room delivery as an upsell — explore partnering with a supplier.